Our development programme so far:
| Contract | Units | Type | Total cost |
|---|---|---|---|
| Phase 1 | 47 units | Full rehabilitation | £1.85 million |
| Phase 1A | 24 units | Full rehabilitation | £0.93 million |
| Phase 2 | 40 units | Full rehabilitation | £1.57 million |
| MSF Security | 432 units | Security installation; Ground floor refurb; Laundry refurb; Water tank renewal; Back stair rewire; Environmentals |
£5.15million |
| MSF Lifts | 432 units | Lift renewal | £1.47 million |
| MSF Rewire | 432 units | Internal rewiring of properties and rewiring of common areas. | £0.9 million (approx) |
| MSF Fabric Works Benmore Bute Arran Ailsa Kintore Roslin |
432 units | Overcladding, re-roofing, new windows Upgraded heating, Upgrade communal TV system, conservatory, stack renewal Kitchen & bathroom renewal (Roslin only) |
£3.4 million £3.4 million £3.5 million £3.5 million £4.3 million £4.3 million |
| New Build | 100 units | New build tenure mix of 2, 3, 4, and 5 apartment properties and environmentals | £13.5 million |
| Total investment to date | £47.77 million | ||
West Whitlawburn Housing Co-operative Ltd